All,
I've a form with a start date and an end date. I use this two dates to calculate the difference in number of work days, excluding weekends and public holidays.
I then have a 'list of sections'. Each section contains a date, and two text fields.
The first date in the list is the start date, then very simply I use the AddDays function to add a new date to the next date picker in the next section.
If I have less than 10 working days, my dates flow as expected.
Once I go over 10 working dates, my date on one field. HDate3 increase by an extra day. I can't figure out why.
The formula is set on HDate 2 as follows: addDays(HDate1, 2). It 's the only field on which the 'jumping' happens.
I've recreated the section and fields numerous times.I can't understand why it would jump.
W