    Q: AddDays extended

    Hello,

    i do not know if this is possible with qrules but here is what we need:

    We have a start date and want to add x-days (duration) to this start date which results in a calculated due date.
    In Infopath we would use the function adddays which works in the first step.

    Here comes the problem:
    If the resulting due date is a non working day (saturday/sunday) it should skip these days and step to the next working days.
    In detail only working days should be used for calculating the duedate.

    Example:

    Start date: Thursday, 28.04.2011
    Duration: 5 Days
    Due date (with normal Adddays function): Tuesday, 03.05.2011
    Correct Due date (without weekend): Thursday,05.05.2011

    Is there a way get this result with the help of qRules?

    Thanks in advance


    Filed under:
  • 04-28-2011 04:30 PM In reply to

    qRules does not have a function that only adds weekdays, but that is a good idea for a possible future feature!

    In the meantime, this blog post may help you with a formula approach.

    Hilary Stoupa

  • 01-27-2012 08:08 AM In reply to

    Between April and now, there wouldn't have happened to be a new release that accounts for this feature would there?

    Thank you for your response.

  • 01-27-2012 08:16 AM In reply to

    No, I'm sorry. We do have that in our list of possible future features, but have not yet implemented it.

    Hilary Stoupa

  • 02-16-2012 10:20 AM In reply to

    Hi - just want to update you - I've gotten the go-ahead to add this to qRules 4.1, which will be released soon!