Im kinda stuck on this issue and im hoping someone here has some advice to help me out.
I have a IP form that allows users to submit new cost savings project ideas and submitting the form kicks off a kinda complex approval workflow up to 4 approvers depending on the department, etc. Everything works great up until it is rejected. Once the project is rejected, the submitting user gets an email to make whatever updates and then will resubmit, continuing at the approval step that the project was rejected at in the workflow. My issue is that when they resubmit the project, it creates a whole second form in the form library and the form that was rejected just sits there, practically a duplicate other than whatever change the user made.
My question is.. Is there a way to update the form and submit without adding a whole new copy of it to the form library?
Also, custom coding is not an option. every bit of logic has to be done in IP and Workflows
Any advice is greatly appreciated.
Thanks