  • 05-06-2010 05:28 AM

    What Formula Would I use to set the Default Value of a InfoPath “Date Field” to 14 days into the future?

    I would like to set the default value in an InfoPath Date Field to 14 days into the future.  I’ve tried many formula combinations, but none of them are returning any sort of date at all – all I get in the filed is either “False” or “NaN”.
    Bruce Burns
    Sr. SharePoint Developer
  • 05-06-2010 07:21 AM In reply to

    Re: What Formula Would I use to set the Default Value of a InfoPath “Date Field” to 14 days into the future?

    set the default value of the field to addDays(today(), 14)

    also uncheck the update this field when the value of the result is recalculated